POWER INTERRUPTION
DATE: January 16, 2020 (Thursday)
Scope of Work: To facilitate the temporary shifting of loads for the reconductoring of #2/0 ACSR to 336.4 MCM wire along Mabalas-Calulut.
TIME:
Part 1: 08:30AM to 01:30PM (5hours)
Part 2: 08:30AM to 09:30AM (1hour)
12:30PM to 01:30PM (1hour)
Part 1: 08:30AM to 01:30PM
Affected Areas:
Citta De Sol
Affected Customers:
RC Cola, Angel Wijangco
Affected LC:
2698 3307 1698 1699 1700 2425 2737 2917 1697 2628 2288 2840 2993
3194
Loads of Bo. Bulaon and Bulaon Resettlement Area, to be temporary transfer to MD04
Part 2: 08:30AM to 09:30AM (1hour)
12:30PM to 01:30PM (1hour)
Affected areas:
Bo. Bulaon, Bulaon Resettlement Area
Affected LC:
1701 1702 2563 3746 3828 1703 1704 1705 1706 1707 1708 1710 1712
1806 2250 3261 595 1811 1812 2279 3569 1810 3288 1363 1809 1813
1805 1814 1808 3515 1807 1819 2338 1715 1717 1817 1818 1820 1850
1722 1723 1774 2215 2220 2857 3230 3279 3471 3602 3737 1337 1338
1339 1718 1720 1724 1740 1741 1764 1765 1766 1945 3150 3392 3644
3665 3721 1721 1725 1742 1748 1768 1769 3252 3725 3851 1726 1729
1733 1752 1771 1772 1775 2438 3257 3302 3414 3688 1730 1734 1749
1753 1754 1770 1787 2751 3253 3431 1727 1731 1732 1735 1750 1751
1755 1758 2934 1728 1759 1777 3018 3151 3578 3667 3703 1336 1736
1743 1756 1757 1776 2213 3848 1737 1738 1744 1970 2118 3178 1739
1745 1760 1746 1951 2180 2309 3415 3596 1747 1761 3009