NGCP POWER ADVISORY: 🙂
National Grid Corporation of the Philippines (NGCP) has scheduled Power Interruption of ALL our consumers in Floridablanca and Basa Air Base to facilitate the following activities:
*Installation of new HVE (DS &PCB) in relation to the upgrading project of Hermosa 69kV Switchyard to breaker and a half scheme;
*Uprating of underrated conductors at 69kV Bus A and uprating of 69kV Bus A PCB;
*Transfer of Hermosa-Guagua 69kV Line from 100MVA Transformer 2 to 300MVA Transformer 1 to anticipate possible overloading of 100MVA Transformer 2;
*Transfer of SFELAPCO-Floridablanca from Hermosa-Guagua Line to Hermosa-Floridablanca 69kV Line to anticipate possible overloading of Hermosa-Guagua 69kV Line;
*Correction of various hotspots at Hermosa Substation
When: MAY 5, 2020 TUESDAY
Time: 6AM to 6PM
Note: Please consider our lines energized at all times. We may restore power earlier than scheduled upon completion of NGCP's works.
Thanks!