(Posted on November 7, 2019)
NGCP POWER INTERRUPTION
When: November 13, 2019 (Wednesday)
Time: 12:01am – 4:00am
Re: Shutdown of Mexico-San Fernando 69KV Line 1
Scope of Work:
- Cut-in of Current Transformer inputs and testing of Stage 2 Tripping relative to the commissioning of Breaker Failure Relays of Power Circuit Breakers prior to start of 2019 SEA Games.
- Verification Testing and General Maintenance of associated High Voltage Power Equipment & Secondary Devices.
- Correction of non-compliant conduits of SFELAPCO Totalizer A & B metering points.
Affected Customers:
ALL SFELAPCO customers supplied by Magdalena & Greenville Substations