POWER INTERRUPTION
Date: May 18, 2019
Time: 8:30 am – 2:00 pm ( 5.5 Hours )
Scope of Work: Revise Primary line configuration, Relocate Primary line on new erected poles, Pullout unused poles along San Isidro way to Alasas CSFP
Affected Customer/’s:
Havana Residences, Sanctuario de San Fernando Memorial Gardens, Jack Bilt Industires Inc., Solana Country Homes, De Leon Farm, Bo. Alasas, Bo. San Isidro, Banlic, Makabakle, West Cavern Subd., Ernesto Ocampo Poultry, Latierra Solana
Please consider our lines energized at all times. We may restore power much earlier right after we have finished our works.