SFELAPCO POWER INTERRUPTION
c/o E# 13011 - 69KV Line 3
When: May 6, 2017 (Saturday)
PART 1
Time: 4:00AM to to 6:00AM
Affected Area/s or Customer/s:
- Feeder 1
- Feeder 2
To facilitate the following:
- Installations of disconnecting knife switches along the primary lines infront Lelut Baculud and Bulaklak Village Gate 2 for Feeder 2.
- Open loop/jumper primary lines for Feeder1
PART 2
Time: 6:00AM to to 7:00AM (“Between”)
Affected Area/s or Customer/s:
- Feeder 15
- Feeder 16
To facilitate the following:
- Transfer loads of Feeder 1 to Feeder 16
- Transfer portions of Feeder 2 to Feeder 15
PART 3
Time: 4:00AM to to 8:00AM
Affected Area/s or Customer/s:
- San Fernando Subdivision
To facilitate the following:
- Replacement of wooden crossarms to steel crossarms near Petron (Sto. Nino) Gas Station
PART 4
Time: 4:00AM to to 12:00NN
Affected Area/s or Customer/s:
- Pasudeco Land Holdings
- Parts of Sto Nino along former Pasudeco (Transformer LC#1603)
To facilitate the following:
- Erections of 90ft (Segmented) concrete poles near Kit Ty Machine Shop going to Gulf Gas Station